RULE 11 - TIME

Section 1. Computation. - Except as otherwise provided by law, in computing any period of time prescribed or allowed by these rules, or any other Commission rule, regulation, or order, or by any applicable law, the day of the act, event, or default from or after which the designated period of time begins to run shall not be included, but the last day of the period so computed shall be included, unless it is a Saturday, Sunday, or a legal holiday, in which event the period shall run until the end of the next working day.
 
Section 2. Extensions. - Except as otherwise provided, whenever by any Commission rule, regulation, or order, or any notice given thereunder, an act is required or allowed to be done at or within a specified time, the time fixed or the period of time prescribed may, for good cause, be extended by the Commission upon the filing of a motion, prior to the expiration of the applicable period of time, showing that there is good cause for such extension of time.
 
Section 3. Continuance. - The Commission or presiding officer may, for good cause at any time, with or without request, continue or adjourn any hearing. A hearing before the Commission shall begin at the time and place fixed in an order or a notice, but thereafter may be adjourned from time to time or from place to place by the Commission or the presiding officer.

 

Today at ERC
Wednesday, September 20, 2017

Hearing Schedules
Time:
10:00
Case No.:
2017-064 CF [JU] [EX] [PT] [EV]
Applicant:
MASELCO
Venue:
ERC Hearing Room (15th Floor)
Title:
Application for Confirmation and Approval of Calculations of Over or Under Recoveries in the Implementation of Automatic Cost Adjustments and True Up Mechanisms Covering the Period 2014 to 2016, Pursuant to ERC Resolution No. 16, Series of 2009, As Amended by ERC Resolution No. 21, Series of 2010 and ERC Resolution No. 2013, Series of 2010
Time:
10:00
Case No.:
2015-223 RC [JU] [EX] [PT] [EV]
Applicant:
TRANSCO, DANECO & DLPC
Venue:
ERC Mindanao Field Office, Mintrade Bldg., Monteverde Avenue corner Sales Street, Davao City
Title:
Application for the Approval of the Sale of Various Sub-transmission Lines/Assets of the National Transmission Corporation (TRASCO) to the Consortium of Davao del Norte Electric Cooperative, Inc. (DANECO) and Davao Light and Power Company, Inc. (DLPC) as Covered by a Contract to Sell dated 06 March 2012
Time:
14:00
Case No.:
2017-054 CF [JU] [EX] [PT] [EV]
Applicant:
BATELEC II
Venue:
ERC Hearing Room (15th Floor)
Title:
Application for Confirmation and Approval of Calculations of Over or Under Recoveries in the Implementation of Automatic Cost Adjustments and True Up Mechanisms Covering the Period 2014 to 2016, Pursuant to ERC Resolution No. 16, Series of 2009, As Amended by ERC Resolution No. 21, Series of 2010 and ERC Resolution No. 23, Series of 2010
Time:
9:00
Case No.:
2017-042 RC [Pubcon]
Applicant:
PEMC
Venue:
Main Conference Room of Mindanao Development Authority Office, Old Airport Building, Old Airport Road, Km 9 Sasa, Davao City, 8000
Title:
Application for the Approval of the Price Determination Methodology for the Wholesale Electricity Spot Market (WESM)

© 2017 - Energy Regulatory Commission