Republic of the Philippines

ENERGY REGULATORY COMMISSION

A world class and independent electric power industry regulator that equitably promotes and protects the interests of consumers and other stakeholders, to enable the delivery of long-term benefits that contribute to sustained economic growth and an improved quality of life.


Notice of Public Hearing, ERC Case No. 2018-095 RC

In the Matter of the Application for Confirmation of Force Majeure Event Capital Expenditure Project, Re: Replacement of Utilized Distribution Line Materials and Equipment, Service Drop Wires and KWH Meters; Replacement of SF6 Breaker, Office Facilities, Furnitures and Equipment, and Construction of New Main Office Building Due to Damage Caused by Tropical Depression Auring and 6.7 Magnitude Earthquake, Surigao Del Norte Electric Cooperative, Inc. (SURNECO) applicant


NOPH_ERCCaseNo.2018-095RC
InitialOrder_ERCCaseNo.2018-095RC

 

Today at ERC
Thursday, January 17, 2019

Hearing Schedules
Time:
09:00
Case No.:
2018-104 RC [JU] [EX] [PT] [EV]
Applicant:
DORECO
Venue:
DORECO's Principal Office, National Highway, Madang, Mati, Davao Oriental
Title:
In the Matter of the Application for Confirmation and Approval of Emergency Capital Expenditure Projects for 2018, Namely: (1) Purchase, Installation and Commissioning of 5 MVA Power Substation and Accessories for Cateel Substation and (2) Purchase of New 10 MVA Power Transformer for Lupon Substation, with Application for Authority to Secure Loan from the National Electrification Administration (NEA)
Time:
10:00
Case No.:
2018-099 RC [JU] [EX] [PT] [EV]
Applicant:
TRANSCO & COTELCO-PPALMA
Venue:
COTELCO-PPALMA Main Office, Villarica, Midsayap, Province of Cotabato
Title:
In the Matter of the Application for the Approval of the Sale of Various Sub-Transmission Lines/Assets of the National Transmission Corporation (TRANSCO) to Cotabato Electric Cooperative Inc.-PPALMA (COTELCO-PPALMA), as covered by a Lease Purchase Agreement (LPA) dated 11 June 2018

© 2019 - Energy Regulatory Commission