RULE 11 - TIME

Section 1. Computation. - Except as otherwise provided by law, in computing any period of time prescribed or allowed by these rules, or any other Commission rule, regulation, or order, or by any applicable law, the day of the act, event, or default from or after which the designated period of time begins to run shall not be included, but the last day of the period so computed shall be included, unless it is a Saturday, Sunday, or a legal holiday, in which event the period shall run until the end of the next working day.
 
Section 2. Extensions. - Except as otherwise provided, whenever by any Commission rule, regulation, or order, or any notice given thereunder, an act is required or allowed to be done at or within a specified time, the time fixed or the period of time prescribed may, for good cause, be extended by the Commission upon the filing of a motion, prior to the expiration of the applicable period of time, showing that there is good cause for such extension of time.
 
Section 3. Continuance. - The Commission or presiding officer may, for good cause at any time, with or without request, continue or adjourn any hearing. A hearing before the Commission shall begin at the time and place fixed in an order or a notice, but thereafter may be adjourned from time to time or from place to place by the Commission or the presiding officer.

 

Today at ERC
Thursday, November 14, 2019

Hearing Schedules
Time:
10:00
Case No.:
2018-103 RC [PT] [EV]
Applicant:
NPC
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Petition for the Availment of the Environment Charge/Share from the Universal Charge for the Rehabilitation and Management of Watershed Areas (Plan 15), with Prayer for Provisional Authority
Time:
10:00
Case No.:
2010-026 MC [CH]
Applicant:
ALECO
Venue:
ERC Hearing Room (15th floor)
Title:
For: Request for Arbitration with a Prayer for a Cease and Desist Order
Time:
10:00
Case No.:
2019-059 RC [JU] [EX] [PT] [EV]
Applicant:
CANORECO
Venue:
CANORECO's Main Office, J. P. Rizal St., Daet, Camarines Norte
Title:
In the Matter of the Application for Confirmation and Approval of Emergency Capital Expenditure Project Re: Purchase and Installation of New 10 MVA Power Transformer in Replacement of Damaged 5 MVA Power Transformer at Calintaan Substation
Time:
10:00
Case No.:
2019-065 RC [JU] [EX] [PT] [EV]
Applicant:
ILPI
Venue:
ILPI Main Office, Bro. Raymund Jeffrey Road, Pala-o, Iligan City
Title:
In the Matter of the Application for the Approval of Electric and Non-Electric Capital Projects for the Regulatory Year 2020
Time:
10:00
Case No.:
2019-074 RC [JU] [EX] [PT] [EV]
Applicant:
BISELCO & CIPC
Venue:
BISELCO’s Principal Office at Barangay Poblacion 6, Coron, Palawan
Title:
In the Matter of the Application for Approval of the Interim Power Supply Agreement Between Busuanga Island Electric Cooperative, Inc. (BISELCO) and Calamian Island Power Corporation (CIPC) with Motion for Provisional Authority
12