RULE 14 - PROVISIONAL AUTHORITY

Section 1. Motions for Provisional Authority. - For applications or petitions covered by Section 1 of Rule 6, the motion for provisional authority shall be included in the application or petition and the caption of the pleading shall clearly indicate that such relief is requested.
 
Section 2. Allegations in Support of the Motion and Supporting Documents. - The motion must be accompanied by supporting affidavits and documents and must allege such facts and circumstances as would justify the Commission’s exercise of discretion by granting provisional authority or interim relief prior to a final decision.
 
Section 3. Action on the Motion. - Motions for provisional authority or interim relief may be acted upon with or without hearing. The Commission shall act on the motion on the basis of the allegations of the application or petition and supporting documents and other evidences that applicant or petitioner has submitted and the comments or opposition filed by any interested person, if there be any.
 
For motions filed in applications or petitions covered by Section 1 of Rule 6, the Commission shall hold in abeyance its resolution of the motion until after the lapse of thirty (30) days from the receipt of a copy of the application or petition by the LGU Legislative Body concerned or publication of the application or petition in a newspaper of general circulation, whichever comes later. The Commission shall also resolve the motion within seventy-five (75) days from the filing of the application or petition. If the Commission issues a provisional authority, it shall schedule and start the hearing on the application or petition within thirty (30) days from date of issuance of the provisional authority and resolve the same within twelve (12) months from the issuance of the provisional authority.
 
Section 4. Refund. - The interim relief granted by the Commission shall be subject to refund if the Commission finds after the hearing on the application or petition that the applicant or petitioner was not entitled thereto or to the full amount of any provisional rate adjustment allowed and to such other conditions that the Commission may impose.

 

Today at ERC
Thursday, November 14, 2019

Hearing Schedules
Time:
10:00
Case No.:
2018-103 RC [PT] [EV]
Applicant:
NPC
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Petition for the Availment of the Environment Charge/Share from the Universal Charge for the Rehabilitation and Management of Watershed Areas (Plan 15), with Prayer for Provisional Authority
Time:
10:00
Case No.:
2010-026 MC [CH]
Applicant:
ALECO
Venue:
ERC Hearing Room (15th floor)
Title:
For: Request for Arbitration with a Prayer for a Cease and Desist Order
Time:
10:00
Case No.:
2019-059 RC [JU] [EX] [PT] [EV]
Applicant:
CANORECO
Venue:
CANORECO's Main Office, J. P. Rizal St., Daet, Camarines Norte
Title:
In the Matter of the Application for Confirmation and Approval of Emergency Capital Expenditure Project Re: Purchase and Installation of New 10 MVA Power Transformer in Replacement of Damaged 5 MVA Power Transformer at Calintaan Substation
Time:
10:00
Case No.:
2019-065 RC [JU] [EX] [PT] [EV]
Applicant:
ILPI
Venue:
ILPI Main Office, Bro. Raymund Jeffrey Road, Pala-o, Iligan City
Title:
In the Matter of the Application for the Approval of Electric and Non-Electric Capital Projects for the Regulatory Year 2020
Time:
10:00
Case No.:
2019-074 RC [JU] [EX] [PT] [EV]
Applicant:
BISELCO & CIPC
Venue:
BISELCO’s Principal Office at Barangay Poblacion 6, Coron, Palawan
Title:
In the Matter of the Application for Approval of the Interim Power Supply Agreement Between Busuanga Island Electric Cooperative, Inc. (BISELCO) and Calamian Island Power Corporation (CIPC) with Motion for Provisional Authority