Republic of the Philippines

ENERGY REGULATORY COMMISSION

A world class and independent electric power industry regulator that equitably promotes and protects the interests of consumers and other stakeholders, to enable the delivery of long-term benefits that contribute to sustained economic growth and an improved quality of life.


Invitation to submit comments on the Resolution Enjoining Compliance with the DOE Circular No. DC2012-03-004, Entitled "Directing Compliance with the Electric Power Industry Reform Act of 2001 (EPIRA) to Address the Power Supply Situation Including the Rationalization of the Available Capacities in the Mindanao Grid and Providing for Fines and Penalties for Violations Therefor" [Archive-174]

Notice is hereby given that on April 2, 2012, the Commission issued "A Resolution Enjoining Compliance with the Department of Energy (DOE) Circular No. DC2012-03-004, Entitled "Directing Compliance with the Electric Power Industry Reform Act of 2001 (EPIRA) to Address the Power Supply Situation Including the Rationalization of the Available Capacities in the Mindanao Grid and Providing for Fines and Penalties for Violations Therefor", which is hereby posted for comment.
 
All interested parties may submit their comments (in both hard and soft copies) on the said Resolution using the prescribed format at the ERC Main Office at Pacific Center Building, San Miguel Avenue, Pasig City, not later than April 10, 2012. Electronic copies may be sent to legal@erc.gov.ph.
 
The said Resolution may be photocopied at cost, during regular office hours at the ERC Main Office or may be downloaded from the ERC website at www.erc.gov.ph.

Date Published: 4/3/2012

 

Today at ERC
Thursday, November 21, 2019

Hearing Schedules
Time:
10:00
Case No.:
2019-068 RC [JU] [EX] [PT] [EV]
Applicant:
IEC
Venue:
IEC’s Principal Office, Metro-Rei Business Park, Brgy. Palindan, Ibaan, Batangas
Title:
In the Matter of the Application for the Approval of the Capital Expenditure Projects of Ibaan Electric Corporation (IEC) for the Years 2013 to 2018
Time:
10:00
Case No.:
2019-072 RC [JU] [EX] [PT] [EV]
Applicant:
ANECO
Venue:
ANECO's Main Office, Km. 2, J. C. Aquino Avenue, Butuan City, Agusan del Norte
Title:
In the Matter of the Application for the Approval of the Generation Rate for the Use (Acquisition and Operation) of Five (5) Units of Two (2) MW Modular Generation Sets and the Corresponding Loan from the National Electrification Administration (NEA)
Time:
14:00
Case No.:
2018-014 MC [EV]
Applicant:
NGCP
Venue:
ERC Hearing Room (15th floor)
Title:
Petition for the Approval of the Extension of the Period for Listing of the Shares of Stock of the National Grid Corporation of the Philippines
Time:
14:00
Case No.:
2019-025 MC [JU] [EX] [PT] [EV]
Applicant:
ELPI
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Application for Authority to Develop, Own and Operate a Dedicated Point-to- Point Limited Transmission Facilities to Connect the 100MW Pasuquin Solar Power Plant to the National Grid Corporation of the Philippines Laoag 115 KV Substation, with Prayer for Provisional Authority