Notice of Virtual Hearing, ERC Case No. 2021-003 MC

In the Matter of the Application for Authority to Develop, Own and/or Operate Dedicated Point to Point Limited Transmission Facilities to Connect the 60 MW Maibarara Geothermal Power Plant Project to the Luzon Grid Through the NGCP Makban – Calamba 69 KV Line, with Prayers for Confirmation of the Classification of the NGCP Makban-Calamba 69 KV Line as a Transmission Asset, Prayers for Provisional Authority, and Interim Relief, Maibarara Geothermal Inc. (MGI) applicant

InitialOrder_2021-003MC
NVH_2021-003MC

 

Today at ERC
Friday, May 20, 2022

Hearing Schedules
Time:
09:00
Case No.:
2022-019 RC [JU] [EX]
Applicant:
MEPC & KEPCO
Venue:
Virtual Hearing: Platform - MS TEAMS
Title:
PSA
Time:
09:00
Case No.:
2022-008 MC [PT] [EV]
Applicant:
FORT PILAR (PITOGO BESS)
Venue:
Virtual Hearing: Platform - MS TEAMS
Title:
PTP
Time:
14:00
Case No.:
2016-196 RC [JU] [EX]
Applicant:
NGCP
Venue:
Virtual Hearing: Platform - MS TEAMS
Title:
CAPEX/FM
Time:
14:00
Case No.:
2022-021 RC [JU] [EX]
Applicant:
CEDC
Venue:
Virtual Hearing: Platform - MS TEAMS
Title:
CAPEX
Time:
14:00
Case No.:
2022-015 RC [EX]