Promulgated Rules, Decisions and Orders


Order, ERC Case No. 2018-019-MC In the Matter of the Application for the Issuance of a Certificate of Public Convenience and Necessity for the Operation of the Electric Distribution System for Iloilo City, with a Prayer for Provisional Authority, MORE ELECTRIC AND POWER CORPORATION (MORE)
Date Docketed:3/16/2020
Published: 3/16/2020


Order, ERC Case No. 2019-080 RC, IN THE MATTER OF THE APPLICATION FOR THE APPROVAL OF THE POWER SUPPLY AGREEMENT (PSA) BETWEEN MANILA ELECTRIC COMPANY (MERALCO) AND SOUTH PREMIERE POWER CORPORATION (SPPC) WITH PRAYER FOR PROVISIONAL AUTHORITY. AND/OR INTERIM RELIEF AND MOTION FOR CONFIDENTIAL TREATMENT OF INFORMATION, MANILA ELECTRIC COMPANY (MERALCO) AND SOUTH PREMIERE POWER CORPORATION (SPPC),
Date Docketed:3/16/2020
Published: 3/16/2020


Order, ERC Case No. 2019-081 RC, IN THE MATfER OF THE APPLICATION FOR THE APPROVAL OF THE POWER SUPPLY AGREEMENT (PSA) BETWEEN MANILA ELECTRIC COMPANY (MERALCO) AND SOUTH PREMIERE POWER CORP. (SPPC), WITH PRAYER FOR PROVISIONAL AUTHORITY AND/OR INTERIM RELIEF AND MOTION FOR CONFIDENTIAL TREATMENT OF INFORMATION, MANILA ELECTRIC COMPANY (MERALCO) AND SOUTH PREMIERE POWER CORP. (SPPC)
Date Docketed:3/16/2020
Published: 3/16/2020


Order, ERC Case No. 2019-082 RC, IN THE MATTER OF THE APPLICATION FOR THE APPROVAL OF THE POWER SUPPLY AGREEMENT (PSA) BETWEEN MANILA ELECTRIC COMPANY (MERALCO) AND FIRST GEN HYDRO POWER CORPORATION (FGHPC) WITH PRAYER FOR PROVISIONAL AUTHORITY AND/OR INTERIM RELIEF AND MOTION FOR CONFIDENTIAL TREATMENT OF INFORMATION, MANILA ELECTRIC COMPANY (MERALCO) AND FIRST GEN HYDRO POWER CORPORATION (FGHPC)
Date Docketed:3/16/2020
Published: 3/16/2020


Order, ERC Case No. 2019-083 RC, IN THE MATTER OF THE APPLICATION FOR THE APPROVAL OF THE POWER SUPPLY AGREEMENT (PSA) BETWEEN MANILA ELECTRIC COMPANY (MERALCO) AND SAN MIGUEL ENERGY CORPORATION (SMEC), WITH PRAYER FOR PROVISIONAL AUTHORITY AND/OR INTERIM RELIEF AND MOTION FOR CONFIDENTIAL TREATMENT OF INFORMATION, MANILA ELECTRIC COMPANY (MERALCO) AND SAN MIGUEL ENERGY CORPORATION (SMEC),
Date Docketed:3/16/2020
Published: 3/16/2020



Order, ERC Case No. 2010-021 RC, In the Matter of the Application for Approval of the Power Supply Agreement Between Ibaan Electric and Engineering Corporation and Thermal Luzon, Inc. with Prayer for Provisional Authority, Ibaan Electric and Engineering Corporation (IEEC) and Therma Luzon, Inc. (TLI) applicants
Date Docketed:3/12/2020
Published: 3/12/2020



Order, ERC Case No. 2019-003 DR, Petition for Dispute Resolution (With Urgent Application for Provisional Relief), Western Mindanao Power Corporation (WMPC) petition versus Zamboanga City Electric Cooperative, Inc. (ZAMCELCO) respondent
Date Docketed:3/12/2020
Published: 3/12/2020



Order, ERC Case No. 2011-033 RC, In the Matter of the Application for the Approval of the Power Supply Agreement (PSA) Between Camarines Sur II Electric Cooperative, Inc. and Therma Luzon, Inc., with Prayer for Provisional Authority, Camarines Sur II Electric Cooperative, Inc. (CASURECO II) applicant
Date Docketed:3/12/2020
Published: 3/12/2020



Order, ERC Case No. 2010-144 RC, In the Matter of the Application for the Approval of the Power Supply Agreement Entered Into By and Between Cabanatuan Electric Corporation and Therma Luzon, Inc. with Prayer for the Immediate Issuance of a Provisional Authority, Cabanatuan Electric Corporation (CELCOR) and Therma Luzon, Inc. (TLI) applicants
Date Docketed:3/12/2020
Published: 3/12/2020



Order, ERC Case No. 2018-086 RC, In the Matter of the Application for the Approval of the Proposed Rates for the Continued Operations and Maintenance of the 24MW Bunker Fired Power Plant Owned by the Cabanatuan Electric Corporation, with Prayer for the Issuance of a Provisional Authority or Interim Relief, Cabanatuan Electric Corporation (CELCOR) applicant
Date Docketed:3/12/2020
Published: 3/12/2020

12345678910...>>

WORKS IN PROGRESS

CaseNoTitleApplicantDate PostedDate Docketed
2019-102 RCIn the Matter of the Application for the Approval of the Three (3) Year Capital Expenditure Projects for the Years 2019 to 2021, and for Authority to Secure Loan, with Prayer for Provisional AuthorityIsabela II Electric Cooperative Inc. (ISELCO II)12/27/201912/27/2019
2019-099 RCIn the Matter of the Application for the Approval of the Power Supply Agreement (PSA) Between Manila Electric Company (MERALCO) and Therma Luzon, Inc. (TLI) with Motion for Confidential Treatment of Information Manila Electric Company (MERALCO) and Therma Luzon, Inc. (TLI)12/23/201912/23/2019
2019-098 RCIn the Matter of the Application for Approval of Capital Expenditure Projects for Calendar Year 2019, with Prayer for Provisional Authority Davao Light and Power Company, Inc. (DLPC)12/20/201912/20/2019
2019-097 RCIn the Matter of the Application for the Approval of the Unplanned Capital Expenditure 2019 Projects of Misamis Oriental Rural Electric Service e Cooperative, Inc. (MORESCO I) Arising from the Immediate New of Industrial / Commercial Customers Power Supply with Prayers for the Issuance of Provisional Authority and to Secure Loan from the National Electrification Administration (NEA) and Private lending InstitutionsMisamis Oriental Rural Electric Service e Cooperative, Inc. (MORESCO I)12/20/201912/20/2019
2019-096 RCIn the Matter of the Application for Approval of Capital Projects for the Years 2017 to 2019 in Accordance with the Rules for the Approval of Regulated Entities' Capital Expenditure Projects and Authority to Secure Loan from NEAPampanga II Electric Cooperative, Inc. (PELCO II)12/20/201912/20/2019
2019-095 RCIn the Matter of the Application for the Approval of the Sale of Various Sub-Transmission Lines / Assets of the National Transmission Corporation (TRANSCO) to Agusan Del Sur Electric Cooperative, Inc. (ASELCO), as Covered by a Lease Purchase Agreement (LPA) dated 15 October 2019National Transmission Corporation (TRANSCO) and Agusan del Sur Electric Cooperative, Inc. (ASELCO)12/20/201912/20/2019
2019-094 RCIn the Matter of the Application for the Approval of the Sale of Various Sub-Transmission Lines / Assets of the National Transmission Corporation (TRANSCO) to Cebu I Electric Cooperative, Inc. (CEBECO I), as Covered by a Contract to Sell dated 25 September 2019National Transmission Corporation (TRANSCO) and Cebu I Electric Cooperative, Inc. (CEBECO I)12/20/201912/20/2019
2019-091 RCIn the Matter of the Application for Approval of Its Capital Expenditure Program for Regulatory Year (RY) 2020Angeles Electric Corporation (AEC)12/13/201912/13/2019
2019-090 RCIn the Matter of the Application for the Approval of the Contingency Project for the Relocation of Electrical Facilities in Connection with the Implementation of Various BBB Projects of the Department of Transportation (DOTr)Manila Electric Company Inc. (MERALCO)12/12/201912/12/2019
2019-089 RCIn the Matter of the Application for Confirmation and Approval of Emergency Capital Expenditure Project, Namely: Construction of New 13.2 KV Three-Phase Primary Backbone Line of Feeder 14 of Boracay Substation Aklan Electric Cooperative, Inc. (AKELCO)11/29/201911/29/2019
1234567

 DISTRIBUTION SECTOR

Distribution Sector. The distribution of electricity to end-users shall be a regulated common carrier business requiring a national franchise. Distribution of electric power to all end-users may be undertaken by private distribution utilities, cooperatives, local government units presently undertaking this function and other duly authorized entities, subject to regulation by the ERC. (Sec. 22, RA 9136)

Distribution Utility refers to any electric cooperative, private corporation, government-owned utility or existing local government unit which has an exclusive franchise area to operate a distribution system in accordance with this Act. (Sec. 4 q, RA 9136) Utilities, including grid interconnections and ancillary services. (Sec. 8, RA 9136)

Downloadable Files

DISTRIBUTION UTILITY MAP

   

 


© 2020 - Energy Regulatory Commission