Promulgated Rules, Decisions and Orders


Order, ERC Case No. 2019-001 MC, In the Matter of the Application for Authority to Develop, Own and Operated Dedicated Point-to-Point Limited Facilities to Connect the Palayan Binary Power Plant to the Luzon Grid, with prayer for Provisional Authority, Bac-Man Geothermal Inc. (BGI) applicant
Date Docketed:7/26/2021
Published: 7/26/2021


Order, ERC Case No. 2019-015 MC, In the Matter of the Application for Authority to Develop, Own and/or Operate Dedicated Point-to-Point Limited Facilities to Connect the 25MW Biomass Power Plant to the Visayas Grid Via the Cadiz Substation of the National Grid Corporation of the Philippines (NGCP) Through the Cadiz-Ipi 69 KV Line, with Prayer for the Provisional Authority, North Negros Biopower, Inc. (NNBP) applicant
Date Docketed:7/16/2021
Published: 7/16/2021


Initial Order, ERC Case No. 2021-021 MC, In the Matter of the Application for Authority to Develop, Own, and Operate Dedicated Point- to-Point Limited Facilities to Connect the Mindanao 3 (M3 Binary) Geothermal Power Project to the Mindanao Grid, with Prayer for Provisional Authority, Energy Development Corporation (EDC) Applicant
Date Docketed:7/13/2021
Published: 7/13/2021


Decision, ERC Case No. 2017-017 MC, In the Matter of the Application for Authority to Develop, Own, Operate and Maintain Dedicated Point to Point Limited Facilities to Connect to the Transmission System of National Grid Corporation of the Philippines (NGCP), with Prayer for Provisional Authority, Victorias Milling Company, Inc. (VMCI) applicant
Date Docketed:7/6/2021
Published: 7/6/2021


Decision, ERC Case No. 2020-015 MC, In the Matter of the Application for Authority to Develop, Own, Operate and Maintain Dedicated Point-to-Point Limited Facilities to Connect to the Transmission System of National Grid Corporation of the Philippines (NGCP), with Prayer for Provisional Authority, Terasu Energy, Inc. (TERASU) applicant
Date Docketed:7/6/2021
Published: 7/6/2021


Initial Order, ERC Case No. 2021-013 MC, In the Matter of the Application for Authority to Develop, Own, and/or Operate Dedicated Point-to-Point Limited Transmission Facilities to Connect the +20MW Gamu Battery Energy Storage System to the Luzon Grid Via the Gamu 69KV Substation of the National Grid Corporation of the Philippines, with Prayer for Provisional Authority and Confidential Treatment of Information, Universal Power Solutions, Inc. (UPSI) applicant
Date Docketed:6/24/2021
Published: 6/24/2021


Initial Order, ERC Case No. 2021-019 MC, In the Matter of the Application for Authority to Develop, Own and/or Operate Dedicated Point-to-Point Limited Transmission Facilities to Connect the ±20 MW Villanueva Battery Energy Storage System to the Mindanao Grid Via the Villanueva 138 KV Substation of the National Grid Corporation of the Philippines, with Prayer for Provisional Authority and Confidential Treatment of Information, Universal Power Solutions, Inc. (UPSI) applicant
Date Docketed:6/22/2021
Published: 6/22/2021


Decision, ERC Case No. 2020-007 MC, In the Matter of the Application for Authority to Develop, Own and Operate Dedicated Point-to-Point Limited Transmission Facilities to Connect the Power Plant Project of Ingrid Power Holdings, Inc, (IPHI) to the 230 KV Malaya Substation of the National Grid Corporation of the Philippines (NGCP), with Prayer for Provisional Authority or Interim Relief, Ingrid Power Holdings, Inc, (IPHI) applicant
Date Docketed:6/21/2021
Published: 6/21/2021


Initial Order, ERC case No. 2021-018 MC, In the Matter of the Application for Authority to Develop, Own and/or Operate Dedicated Point-to-Point Limited Transmission Facilities to Connect the ±20 MW Toledo Battery Energy Storage System to the Visayas Grid Via the Calong-Calong Substation of the National Grid Corporation of the Philippines (NGCP) with Prayer for Provisional Authority and Confidential Treatment of Information, Universal Power Solutions, Inc. (UPSI) applicant
Date Docketed:6/11/2021
Published: 6/11/2021


Order, ERC Case No., 2021-031 RC, In the Matter of the Application for the Approval of the Implementation of Capital Expenditure Program for Calendar Years 2021-2025 (Batch 2), with Prayer for the Issuance of Provisional Authority, National Grid Corporation of the Philippines (NGCP) applicant
Date Docketed:6/11/2021
Published: 6/11/2021

1234567

PROMULGATED RULES

ERC APPROVED ASPA CONTRACTS BETWEEN AS PROVIDER AND NGCP

WORKS IN PROGRESS

CaseNoTitleApplicantDate PostedDate Docketed
2021-061 RCIn the Matter of the Application for Approval of the Feed-In Tariff Allowance for Calendar Year 2022 Pursuant to the Collection of the Feed-In Tariff Allowance and Disbursement of the Feed-In Tariff Allowance Fund, with Prayer for Provisional Authority National Transmission Corporation (TRANSCO)7/29/20217/29/2021
2021-058 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and King Energy Generation, Inc. (Surigao del Sur Power Plant), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP) and King Energy Generation, Inc. (KEGI)7/23/20217/23/2021
2021-056 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and SMCGP Philippines Energy Storage CO. Ltd. (For Regulating Reserve), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP) and SMCGP Philippines Energy Storage Co. Ltd. (SPESCL)7/19/20217/19/2021
2021-051 RCIn the Matter of the Application for the Approval of the Batangas - Mindoro Interconnection Project with Prayer for the Issuance of Provisional Approval National Grid Corporation of the Philippines (NGCP)7/8/20217/8/2021
2021-049 RCIn the Matter of the Application for the Approval of the Quezon - Marinduque Interconnection Project with Prayer for Provisional Approval National Grid Corporation of the Philippines (NGCP)7/8/20217/8/2021
2021-031 RC In the Matter of the Application for the Approval of the Implementation of Capital Expenditure Program for Calendar Years 2021-2025 (Batch 2), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP)4/27/20214/27/2021
2021-008 RCIn the Matter of the Application for the Approval of the Implementation of Lala – Naga – Mindanao – Zamboanga 230 KV Transmission Line Project and Zamboanga Peninsula Voltage Improvement Project (ZPVIP), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP)1/27/20211/27/2021
2021-006 RCIn the Matter of the Application for the Approval of the Implementation of Capital Expenditure Projects for Luzon (Group 2) from 2020-2025 and Beyond, with Payer for the Issuance of Provisional Approval National Grid Corporation of the Philippines (NGCP)1/25/20211/25/2021
2021-005 RCIn the Matter of the Application for the Approval of the Capas 230KV Substation, Porac 230KV Substation, North Luzon Substation Upgrading II Projects, and Acquisition of Transmission Assets with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP)1/25/20211/25/2021
2021-004 RCIn the Matter of the Application for the Approval of the Implementation of Capital Expenditure Program for Calendar Years 2021-2025, with Payer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP)1/18/20211/18/2021
12

 TRANSMISSION SECTOR

Transmission Sector. The transmission of electric power shall be a regulated common electricity carrier business subject to the ratemaking powers of the ERC. (Sec. 7, RA 9136)

Creation of the National Transmission Company. The TRANSCO shall assume the authority of NPC for the planning, construction and centralized operation and maintenace of its high voltage transmission facilities, including grid interconnections and ancillary services. (Sec. 8, RA 9136)